Can I add an Answer Type to a question after evaluation has started, and what happens to existing scores?

Yes, you can assign a different Answer Type to a question after scoring has begun — but if answers already exist for that question, AWARD® treats it as a configuration change that affects those answers. 

What happens depends on your project's Data Protection setting. Note that you cannot change the entry type of an existing Answer Type; instead you assign a different Answer Type to the question.


If answers already exist on the question

Assigning Answer Types to a question is done by an Administrator (Question → Answer Measures → Edit). When you change which Answer Types are assigned to a question that already has answers in the Answer Sheets:

  • With Data Protection ("Protect Data") switched on — the change is blocked. AWARD® shows: "Warning: This is a configuration change which will set any 'Completed' Answers to 'In Progress' in the Answer Sheets. You will need to disable Data Protection to complete this action." You must disable Data Protection before you can proceed.
  • With Data Protection switched off — the change is allowed after you confirm. AWARD® warns: "This action will set 'Completed' Answers to 'In Progress' in the Answer Sheets."

In both cases, the effect on existing scores is the same once the change goes through:

> Existing answers are not deleted and not recalculated — but any that were "Completed" are reset to "In Progress". The evaluators will need to review and re-complete (re-submit) those answers.

If the question has no answers yet, the Answer Type is simply assigned with no warning.


Removing an Answer Type is different — it deletes the scores

Be careful with the opposite action. Removing an Answer Type that already has answers against it deletes those answers (scores). As above, this is blocked while Data Protection is on, and allowed with a confirmation warning when it is off. If an Answer Type is used by a Score Transformation, it cannot be changed or removed at all until that dependency is resolved.


A few rules to be aware of

  • You cannot change the entry type of an existing Answer Type (AWARD® reports "Cannot change type of Answer Type"). To use a different style of answer, assign a different Answer Type to the question.
  • Answer Types can only be assigned to scored (Evaluation) questions — not to the Overall, Lot-root or parent questions.
  • A Cost Question requires a Cost Answer Type (and vice versa). If you assign an Answer Type that doesn't fit the question, that assignment is skipped and recorded in the event log, while any other valid assignments still go through.


Recommendation

Because adding or removing Answer Types after scoring has started will reset or delete evaluators' work, finalise your Answer Types before evaluation begins wherever possible. If you must change them mid-evaluation, tell the affected evaluators first, and keep Data Protection on until you have deliberately decided to make the change.