Overview
You can add a project Start and End Date that is visible to the Evaluators and project administrators from their project home screen. This is used to communicate key dates, for example, the period and the procurement will be running. If no start and end date is entered, the date displays as ‘unspecified’.
Project Start and End Dates can be edited at any time during the procurement lifecycle.
Project Managers View -
Evaluators view –
Guidance
- To add the Project Start and End Dates, navigate to Project > Setup > Tools
- Click on View Project Details
- From the View Project Details page click Edit
- Scroll to the bottom and enter the Start and End Dates as required. You will also need to add a time in the following format- HH:MM
- Once ready click Save to finalise the changes. The changes will be visible immediately.